Yesterday took over the possession of the land and the project was activated.
We surveyed the land got those marking done.
Today, got those backhoe tractor into action. Level the ground and pull a few mangostene and durian trees down.
By end of the day those cement footing holes will be ready for tomorrow's steel bars installation. Once completed will bring in ready mixed cement lorry to pour them in the holes. I will take at least 2 days to solidify.
Will move in a few more workers to get ready the base floor and those side pillars.
If everything goes well, no rain of course, will be able to complete within 6 weeks.
Will need another 2 weeks to install those nesting planks, sound system and testing mode.
Total time required is 2 months. Keep you figure crossed.
Not bad for a simple 2 1/2 stories building.